Cheyyur or Manellore? The Critical Checks Behind Chennai’s Second Airport Decision

Sriharikota airspace, CRZ, bird hazards, forests and building-height limits—what must be examined before either site is selected.

7 Min Read

After dropping the Parandur airport proposal, the Tamil Nadu government has reportedly shortlisted Cheyyur in Chengalpattu district and Manellore near Gummidipoondi in Tiruvallur district for Chennai’s second airport.

Tamil Nadu Industrial Development Corporation Limited (TIDCO) officials have reportedly completed preliminary inspections. The Airports Authority of India (AAI)  is expected to conduct detailed feasibility studies before the government selects a final location.

Why Were Cheyyur and Manellore Shortlisted?

Cheyyur is situated near to southern Chennai, Chengalpattu and Puducherry-side areas, while Manellore is situated near to North Chennai, Tiruvallur and the adjoining Andhra Pradesh industrial belt.

Both locations are also believed to have the potential to provide the large and continuous land required for an airport while reducing the agricultural, environmental and residential impact seen at Parandur. However, the government has not released a comparative study proving these advantages. Their actual suitability will be known only after AAI completes its technical feasibility study.

What are the concerns at Manellore?

Manellore is around 50–60 km from Chennai and approximately 35 km by air from the Sriharikota space centre. AAI must examine whether rocket-launching operations could affect the proposed airport’s air routes.

The study must also check nearby waterbodies, migratory-bird movements, reserve forests and possible CRZ restrictions. Airport-related building-height restrictions could eventually extend several kilometres beyond the runway boundary.

What are the concerns at Cheyyur?

Cheyyur is approximately 100–120 km from the existing Chennai airport, around 40 km from Puducherry airport and about 35 km from Kalpakkam.

Reports indicate that the area may require defence clearance because its airspace is influenced by the Tambaram Air Force Station. Kalpakkam’s prohibited airspace, coastal zones, wetlands and agricultural lands must also be studied.

What Will AAI Check Before Approving an Airport Site?

For a new airport, AAI and Directorate General of Civil Aviation (DGCA) will examine much more than the land inside the proposed boundary. The surrounding region is checked to determine whether aircraft can safely approach, land and depart.

CheckWhat will be examinedWhy it matters
AirspaceNearby civil airports, defence airspace, rocket-launch zones and existing flight routesConflicting airspace may make aircraft operations difficult or unsafe
Runway alignmentWind direction, crosswinds, rainfall, fog, cyclones and visibilityDetermines the safest direction and position of the runway
ObstaclesBuildings, towers, chimneys, power lines, wind turbines, hills, trees and cranesObjects penetrating the airport’s safety surfaces may need height restrictions
Bird hazardsBird sanctuaries, migration routes, wetlands, lakes, fish farms, garbage dumps and slaughterhousesLarge bird movements can increase the risk of bird strikes
TerrainGround elevation, slopes, hills, soil stability and uneven landThe site must safely support runways and airport buildings
Waterbodies and floodingLakes, tanks, rivers, canals, wetlands, drainage channels and historical floodingWaterlogging and flooding can affect runway safety and airport operations
Environmental restrictionsCRZ areas, reserve forests, mangroves, protected wetlands, wildlife sanctuaries and eco-sensitive zonesProtected areas may restrict development or require special clearances
Nearby settlementsVillages, houses, schools, hospitals, temples and heritage structuresHelps assess displacement, aircraft noise and public-safety concerns
Land availabilityContinuous land, ownership, agricultural land, government land and future expansion spaceA large airport needs sufficient land without major physical interruptions
ConnectivityRoads, railways, highways and travel time from the cityThe airport must be easily accessible to passengers and cargo
UtilitiesElectricity, water, fuel supply, communications, drainage and waste managementEssential for construction and continued airport operation
Building-height controlsFuture Colour-Coded Zoning Map and permissible top elevations around the runwayHeight restrictions can affect properties several kilometres beyond the airport fence
Emergency requirementsFire and rescue access, emergency roads, safety zones and nearby medical facilitiesRequired for aerodrome licensing and safe operations
Regulatory approvalsAAI, DGCA, Ministry of Civil Aviation, Ministry of Defence and environmental authoritiesThe project cannot proceed without the necessary clearances and licence

Future building-height restrictions

Once the runway coordinates and elevation are fixed, AAI can prepare a Colour-Coded Zoning Map showing permissible top elevations around the airport. Height-control requirements may extend up to approximately 20 km for a VFR airport or 56 km for an IFR airport, depending on the applicable aviation facilities and regulations

How Long Could the New Airport Take?

The Ministry of Civil Aviation guidelines aim to process site clearance within three months and in-principle approval within another three months after complete applications are submitted. However, defence, environmental, land and public-objection issues can extend this considerably. Ministry of Civil Aviation guidelines

Current reports estimate that land acquisition, approvals and construction may require at least five to seven years after the final site is selected. From the present preliminary-study stage, seven to ten years is a safer overall estimate.

Therefore, even if Cheyyur or Manellore is selected during 2027, the airport is unlikely to become operational immediately; a realistic opening could fall in the early-to-mid 2030s, provided there are no major legal, environmental or land-acquisition delays.

Buyers should avoid airport-based speculation

The government has not released the proposed airport boundaries, affected villages, survey numbers, land requirement or runway alignment. Therefore, advertisements claiming that particular properties are “near the confirmed new airport” may be misleading.

LandLens can help property buyers conduct preliminary checks for CRZ zones, waterbodies, forests and airport-related warnings. However, the actual acquisition area and construction-height restrictions can be confirmed only after the government officially selects and notifies the airport site.

Current status: Cheyyur and Manellore are only under consideration. Neither location has been approved or finalised.